The Transmission Company of Nigeria, TCN hereby states that it’s contractor Shangai Electric Company and TCN engineers are working assiduously to restore the 300MVA power transformer that was shut down by the protective control mechanism at the Lekki Transmission Sub-Station on the 24th of October, 2024.
The protective control triggered the shutdown of the transformer when it started making serious arching sounds with smoke coming out from the red phase of 132kV secondary power cable.
The Aja maintenance crew, subssequently, isolated the power cables from the transformer to enable the system operators to restore the primary side of the transformer.
To ensure we reduce downtime on the transformer, TCN diverted the main power cable meant for the proposed TR2-300MVA, 330/132/33kV transformer to ensure the prompt repair of the existing 300MVA ppwer transformer.
The Shangai Electric Company (contractors) are working with TCN engineers to expedite repairs.
TCN regrets every inconvenience this has caused electricity consumers within the affected areas and appeals for patience from affected customers.
Ndidi Mbah
GM (Public Affairs)
28/10/2024
For more information about Alfijir labarai/Alfijir News follow us onπ
https://twitter.com/Musabestseller?s=09
https://www.facebook.com/profile.php?id=100089640289165
https://www.threads.net/@alfijirlabarai
https://www.youtube.com/@BestsellerChannel12
https://www.instagram.com/musa_bestseller?utm_source=qr&r=nametag
Alfijir labarai Alfijir News Whatsapp Group ππ
https://chat.whatsapp.com/ELQRQyq1zGn7zpAVP8DwNj